Quantcast

The DNAinfo archives brought to you by WNYC.
Read the press release here.

New York Wheel

Recent Headlines
St. George »

American Bridge Company, which built the Las Vegas High Roller, is in talks to finish construction.

St. George »

The $590 million Ferris wheel construction is delayed indefinitely after the contractor's firing.

St. George »

New York Wheel sued builders over threats to pull out of the contract for work.

St. George »

The 460-foot tall crane, which is 170 feet shorter than the wheel will be, was installed last month.

St. George »

The proposed ferry would transport Staten Islanders to West 39th Street, James Oddo said.

St. George »

The parking garage will allow drivers to park their own vehicles as of Monday.

St. George »

Developers settled the suit filed by investor Eric Kaufman.

St. George »

It's the first major part of the above-ground structure to be put in place.

St. George »

The 100-ton pedestals will hold the wheel's legs in place.

St. George »

New York Wheel CEO Rich Marin gave the first 10 tickets to students in an afterschool STEM program.

St. George »

After several delays, the first 820 parking spaces in the garage will open to the public Friday.

St. George »

The time capsule, to be opened in 630 years, contains a newspaper, letters and honey, among other items.

St. George »

Crews laid the foundation that will hold the legs of the Ferris wheel.

St. George »

Investor Eric Kaufman also said CEO Rich Marin has let the budget get out of control.

St. George »

Investor Eric Kaufman claims there is no business plan for the project.